The question behind every kitchen remodel is not really “how long will this take?” It is “how long will my family be without a kitchen?” Those are two different numbers. Most of a remodel’s calendar happens before anyone picks up a pry bar, and the part you actually live through depends on the scope of the job and on one step most homeowners do not know about: the wait between setting the cabinets and installing the countertops. This guide walks through a typical schedule week by week, shows what you can and cannot use at each stage, and explains what tends to stretch it. It applies to homes in Cary, Apex, Holly Springs, Fuquay-Varina and Raleigh.
The short answer
| Scope | Typical time on site | Without a working kitchen? |
|---|---|---|
| Refresh (refaced or painted cabinets, counters, backsplash, fixtures) | 1 to 2 weeks | Partly. The sink is usually down for a few days around the new counters |
| Full remodel, same layout | 6 to 12 weeks | Most of that time, with water and appliances back near the end |
| Layout change (walls, moved plumbing, new island) or custom cabinets | 3 to 8 months from start of planning to finish | Longer on site than a same-layout job, and the planning takes longer too |
These are general industry ranges, not a HomePro schedule. Your written schedule depends on your kitchen, your selections and what is on order.

Before demolition: the part you do not live through
A well-run remodel looks slow at the start because everything is being lined up so the torn-up part is as short as possible. These are the steps and how long each typically takes:
- Design and selections: a few days to about 3 weeks. Longer if a structural engineer or a cabinet maker is involved, and longer again if you are collecting several quotes.
- Permits: about a week or two. Only if the job moves plumbing, adds circuits or changes a wall. Cary, Apex, Holly Springs, Fuquay-Varina and Raleigh each run their own office. Our remodeling permits guide explains who issues what.
- Stock cabinets: about 1 to 2 weeks to arrive.
- Semi-custom cabinets: about 4 to 8 weeks.
- Custom cabinets: anywhere from 6 to 12 weeks to several months, depending on the shop and the order.
- Appliances: a few weeks. Plan for them early, because the cabinet layout has to be built around their exact sizes.
The rule that saves the most grief: do not start demolition until the cabinets, tile, fixtures and appliances are on hand or have firm delivery dates. A kitchen that sits gutted while a truck is late is the experience everyone warns you about, and it is avoidable.
Week by week: a same-layout remodel
Here is how the on-site part commonly runs for a full remodel in the existing layout, with cabinets already delivered. Treat it as an example of the order of work. Real jobs move a little faster or slower at each step.
| When | What happens | What you can use |
|---|---|---|
| Week 1 | Floors and doorways protected, dust barrier up, old cabinets, counters and flooring removed and hauled off | Temporary station only. Fridge moved to another room or the garage |
| Week 2 | Plumbing and electrical roughed in (2 to 4 days), then inspected. Drywall repairs and primer. New flooring if it runs under the cabinets | Temporary station only |
| Week 3 | Cabinets set, leveled and fastened (2 to 3 days). Fabricator comes to template the counters | Temporary station. The room starts to look like a kitchen, but there is no sink yet |
| Weeks 4 and 5 | Counters being fabricated, commonly 10 to 14 days from template to install. Paint, lighting and trim continue | Temporary station. This is the stretch that feels like nothing is happening |
| Week 5 or 6 | Counters installed, usually in a single day. Sink, faucet and dishwasher connected | Water is back. Often the range too, so you can start cooking again |
| Week 6 | Backsplash (a couple of days), remaining appliances, fixtures and hardware | Most of the kitchen, working around the tile work |
| Week 7 | Paint touch-ups, final inspection if a permit was pulled, punch list and walkthrough | Everything |

Why the counters take so long
Countertops are the step that surprises people. A stone or quartz fabricator cannot measure until every cabinet is set and leveled, because the template has to match what was actually built. After that visit, fabrication commonly takes 7 to 14 days when the slab is in local stock. Ten to 14 days from template to install is realistic for a simple job, and 3 to 4 weeks is not unusual in busy months or if the slab has to ship in. Install day itself is only a few hours. Nothing is going wrong during that gap, but it is why a kitchen can look nearly done and still have no sink.
What stretches the schedule
- Moving things. Relocating a sink’s supply and drain lines adds days. Opening a wall adds an engineer, plan review and a beam.
- Surprises behind the walls. Mold, water damage or old wiring only show up once the cabinets are out. Mold remediation alone can add about a week.
- Late materials. Cabinets and appliances are the usual culprits, which is why ordering first matters.
- Changes mid-job. Changing a cabinet after the counters are templated can void the template and restart the wait.
- Inspection scheduling. Rough-in inspections have to pass before the walls close. Apex, for example, asks for inspections to be scheduled by 2 p.m. the day before.
- Subfloor repairs. These can add a day or two before new flooring goes down.

How to live through it
Most families stay in the house during a kitchen remodel. A little setup makes it far easier:
- Set up a temporary kitchen before demolition. Fridge, microwave, coffee maker, toaster oven and a folding table in a dining room, laundry room or garage.
- Plan for dishes. Paper plates cut the work a lot. Otherwise, a laundry sink or bathtub will do.
- Use the grill and the slow cooker. Budget for more takeout than you expect, especially during weeks 4 and 5.
- Pack the kitchen a week ahead. Keep out one pot, one pan and a few basics. Label the boxes you will want first.
- Protect the rest of the house. Ask how dust will be contained and how the HVAC returns near the kitchen will be handled.
- Agree on a daily routine. Start time, where crews park and enter, and who you call when something changes.
Want a real schedule for your kitchen?
HomePro Remodeling gives homeowners in Cary, Apex, Holly Springs, Fuquay-Varina and Raleigh a free in-home visit, then a written proposal with a schedule before any work starts. Call (919) 758-3683 or request a free estimate. See our kitchen remodeling and Cary remodeling pages.
If you need it done by a certain date
Count backward from the date, not forward from today. A same-layout remodel with semi-custom cabinets adds up like this: a few weeks for design and selections, 4 to 8 weeks for cabinets, and 6 to 12 weeks on site. That is roughly 3 to 6 months from first conversation to finished kitchen. So if you want to host in the new kitchen on a particular holiday, start the conversation at least 6 months ahead. Starting demolition close to the date is the worst of both worlds, because any delay lands on the holiday itself.
How to shorten it
- Keep the layout. It removes engineering and much of the plumbing and electrical work. Read our full versus partial kitchen remodel guide.
- Reface instead of replacing, if the cabinet boxes are sound. Our kitchen cabinets page explains when that works.
- Make every selection before ordering, and resist changes once work has started.
- Choose in-stock counters and tile where you can. Special orders add weeks.
Budget and schedule move together. Our cost guides for Cary and Raleigh show what each scope typically costs, and our process page explains how a HomePro project runs.
Kitchen remodel timeline questions
How long will I be without a kitchen?
For a full same-layout remodel, plan on about 5 to 6 weeks without a sink, out of a typical 6 to 12 weeks on site. A refresh that keeps your cabinet boxes is much shorter, usually a few days without a sink. A layout change runs longer.
Can we live in the house during a kitchen remodel?
Usually, yes. With a temporary station and dust barriers, most families stay. It is harder with very small children, or if the remodel is combined with other rooms.
What is the longest part of a kitchen remodel?
Before work starts, it is waiting on cabinets. During work, it is the gap between templating and installing the counters.
Why does my contractor want to order everything before starting?
So the kitchen is not torn apart while materials are on backorder. It makes the start date later and the time without a kitchen shorter, which is the trade most homeowners want.
Does a permit slow things down?
Slightly. It adds about a week or two up front, plus inspections during the job. It is required for plumbing, electrical and structural work, and your contractor should handle it.
What is the most common cause of delays?
Late materials and problems found behind the walls. Ordering early handles the first. Keeping 10 to 15 percent of the budget in reserve, and a little give in your calendar, handles the second.